日前,浙江公司(si)臨平(ping)6號地(di)塊項目地(di)下(xia)首道水平(ping)支撐體完成澆筑。 該項目(mu)設(she)計共2層(ceng)地(di)下室,其中首道支(zhi)撐體C30混凝土澆筑用(yong)量208立方(fang),支(zhi)撐體位于圍(wei)護(hu)樁之(zhi)上,將圍(wei)護(hu)樁與格構柱連接成整體,有效(xiao)防止(zhi)基坑頂部(bu)邊緣產生(sheng)坍塌,保證基坑穩定(ding)。 為確保水平支(zhi)撐體施(shi)(shi)(shi)工(gong)(gong)(gong)進展順(shun)利,項目各(ge)部(bu)門積極配合,制定適合本項目的施(shi)(shi)(shi)工(gong)(gong)(gong)方案,安排合理的施(shi)(shi)(shi)工(gong)(gong)(gong)計劃(hua),在(zai)施(shi)(shi)(shi)工(gong)(gong)(gong)過程中對SMW工(gong)(gong)(gong)法樁壓頂梁和支(zhi)撐梁鋼(gang)筋(jin)(jin)連接(jie)節點(dian)等重點(dian)施(shi)(shi)(shi)工(gong)(gong)(gong)部(bu)位嚴格把控,嚴抓鋼(gang)筋(jin)(jin)數量、鋼(gang)筋(jin)(jin)錨固長度(du)、鋼(gang)筋(jin)(jin)搭接(jie)長度(du)等數據參數,在(zai)推進施(shi)(shi)(shi)工(gong)(gong)(gong)進度(du)的同時確保施(shi)(shi)(shi)工(gong)(gong)(gong)現場處于(yu)可控狀態。 下一步,項(xiang)目部將繼續加強現場管理(li)、施工(gong)質量(liang)和安(an)全(quan)管控,合理(li)安(an)排(pai)后續施工(gong),高質高效完成各項(xiang)節點目標任務。 | |||||